10 exam-style questions with answers and explanations, straight from our 1,054-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.
The CCIFP exam has 200 questions and runs 4 hours 30 minutes.
These 10 free CCIFP questions are organized by exam domain, so you can see how each part of the Certified Construction Industry Financial Professional (CCIFP) blueprint is tested. Reveal the answer and explanation under each question.
Domain 1: Accounting and Reporting 23% of exam
Question 1
A contractor purchases a wheel loader for $240,000. It also pays $17,000 in freight, $36,000 for installation and commissioning, $12,000 in sales tax, and $28,000 for a separately stated three-year preventive maintenance contract. What amount should be recorded as the depreciable basis of the equipment?
Show answer & explanation
Correct answer: B - $305,000
Question 2
A contract has a price of $4,000,000 and estimated total costs of $3,400,000. Costs incurred to date are $1,700,000 and billings to date are $2,100,000. Using the cost-to-cost method, what is the over/(under) billing on this contract?
Show answer & explanation
Correct answer: A - $100,000 overbilled
Question 3
On the balance sheet of a construction contractor, an amount reported as "costs and estimated earnings in excess of billings" represents:
Show answer & explanation
Correct answer: B - A contract asset, because the contractor has performed work it has not yet billed
Question 4
At the end of Q2, a contractor determines that a contract that is 20% complete will result in a total loss of $450,000. How much loss should be recognized in Q2?
Show answer & explanation
Correct answer: B - $450,000
Question 5
A contractor adopts ASC 842 and capitalizes a large fleet of equipment leases previously classified as operating leases. Assuming no other changes, the MOST likely effect on the contractor's balance sheet is that:
Show answer & explanation
Correct answer: C - Working capital decreases, because the current portion of the lease liability is a current liability while the right-of-use asset is non-current
Domain 2: Revenue Recognition Methods 21% of exam
Question 6
A general contractor's $18,000,000 contract to build an office tower includes excavation, structural steel, envelope, MEP systems, and interior finishes. Under ASC 606, this contract is MOST likely accounted for as a single performance obligation because:
Show answer & explanation
Correct answer: C - The contractor provides a significant service of integrating the individual scopes into one combined output, so they are not separately identifiable in the context of the contract
Question 7
A contractor's $6,000,000 contract requires it to procure and install a custom chiller. The chiller costs $900,000, the owner takes control of it on delivery to the site, and it will sit for four months before installation. The contractor did not design or manufacture it and simply arranged its purchase. At delivery, under ASC 606, the contractor should:
Show answer & explanation
Correct answer: C - Recognize revenue equal to the $900,000 cost with zero margin, and exclude the cost from the cost-to-cost measure of progress
Domain 4: Risk Management 13% of exam
Question 8
Which statement BEST distinguishes a surety bond from an insurance policy?
Show answer & explanation
Correct answer: C - A surety bond is a three-party agreement under which the surety expects no losses and retains a right of indemnity against the principal
Question 9
A contractor's workers' compensation loss history shows one severe claim of $600,000 in the experience period. A competitor of similar size and payroll has nine claims totaling $600,000. All other factors are equal. Compared to the competitor, this contractor's experience modification rate will MOST likely be:
Show answer & explanation
Correct answer: A - Lower, because the experience rating formula weights claim frequency more heavily than claim severity
Domain 5: Taxes 6% of exam
Question 10
A subcontract states: "Contractor shall pay Subcontractor within ten days of Contractor's receipt of payment from Owner, receipt of such payment being an express condition precedent to any obligation of Contractor to pay Subcontractor." The Owner becomes insolvent and never pays the Contractor. In a jurisdiction that enforces such clauses, the effect is that:
Show answer & explanation
Correct answer: A - The Subcontractor bears the risk of the Owner's nonpayment and is never entitled to payment under the subcontract